The Tisbury Harbor Department announced Friday the completion of a $66,000 project to extend the Lake Street dinghy docks to help alleviate overcrowding in the summer months.

Despite high winds, the project “went smoothly,” Michael Gately, Tisbury harbormaster, said in a press release. It included efforts by the Martha’s Vineyard Shipyard and John Packer of R.M. Packer Co. The Shipyard delivered three new sections of dock float to Lake Street Landing Thursday, and Packer used his barge to drive in the three pilings, all of which were repurposed from the Owen Park Pier reconstruction. Gately called the reuse of those pilings a “successful foresight” in the planning process.

Lake Tashmoo has more than 350 moorings, many of which are in the Lake Street mooring field, and boaters heavily rely on the dinghy dock and beach strip to store dinghies.

The additions made significant room for more dinghies, Gately said, though he wasn’t sure exactly how many more boats could be stored there.

The project, funded by the Community Preservation Act and the Waterways Infrastructure account, started four years ago, and spans the work of three harbormasters: John Crocker, Gary Kovack, and Gately.

“Even small municipal waterside projects take time,” Crocker said in the release. “This project took several years to complete, but it’s an example of what can be accomplished when the whole boating community works together.” 

The project, first introduced in 2023 by Tashmoo boaters Lynne Fraker and Paul Munafo as well as mooring installer Ray Gale, went under review by the Tisbury Conservation Commission, the Massachusetts Division of Marine Fisheries, the Department of Environmental Protection, and the U.S. Army Corps of Engineers.

Fraker, who voluntarily did the permitting for the project, said she and Munafo “did it for the Tashmoo community,” who she said supported the project more than anyone else. The private donations were “amazing,” said Fraker. She added that Gale passed around a sketch at the project’s inception, and that Gately helped coordinate an eelgrass survey and get the expansion over the finish line.

“It’s been a long time in the works, and it’s finally in place … we compromised a bit to get to where we are,” Munafo said in a text to The Times. “I want to thank all those boaters who contributed to get the original ball rolling to get the project started.”

“This is our second long-planned pier project we have completed in 2026. We are thrilled that both Owen Park Pier and now Lake Street can better serve our waterways,” Gately said in the release.

Editor’s note: Updated with comments from Lynne Fraker and Paul Munafo.

2 replies on “Years-long project for Tisbury dinghy docks completed”

  1. The permitting for this project was funded by private donations, while CPC funds covered the construction. The project began around 2021 with Ray Gale, and we persisted through resistance with overwhelmingly positive public support. Some Town officials didn’t think we needed this, but the Tisbury NRAC recognized the need and supported Paul Munafo and me through the lengthy permit process. Thanks to former Town Administrator Jay Grande for stepping in when we needed him. Former Harbormaster Gary Kovack came in at the right time to support the permitting process. Thanks, Gary. Thanks to Harbormaster Gately, for helping with the final eelgrass issue, the bid process, and extra funding. Thanks to the crews from MV Shipyard and John Packer for installing the dinghy docks ahead of schedule. Special thanks to Paul Munafo, who kept encouraging the process through some difficult times when we were about to give up. And, of course, thanks to the amazing Tashmoo community for all your donations, support, and encouragement. This is for you. It’s not the project we hoped for, and it won’t solve all the problems, but it is a vast improvement and a step in the right direction.