Vineyard Wind 1 has reached full commercial operations, a final milestone in a years-long project that’s experienced multiple setbacks along the way.
“On Thursday, October 29, Vineyard Wind 1 reached full commercial operations, further strengthening New England’s energy supply,” Craig Gilvarg, a Vineyard Wind spokesperson, said in a statement.
A wind farm reaches full commercial operations when every turbine is commissioned, or tested, and is fully online. That means that every turbine should spin, except when taken offline for maintenance.
The project, first selected by Massachusetts in 2018, has experienced rough seas for almost a decade — from a blade that broke off one turbine located at the southernmost tip of the lease area and littered debris on the Cape and Islands to a stop-work order by the current federal administration that paused work for a month. A contractor even threatened to walk out on the project. The project, 15 miles south of the Vineyard, didn’t finish construction on the 62 turbines until March, years after completion was projected.
Announcement of the project’s milestone comes as Revolution Wind, another turbine off the coast of the Island, also reached commercial operations.
Typically when a project reaches full commercial operations, the electricity starts to be sold at a fixed price on the regional open energy market, based on power purchase agreements between the energy producer and buyer like a utility company.
The 20-year contracts between Vineyard Wind and state utilities, National Grid USA, Eversource Energy, and Unitil Corp., however, were activated in April and any energy produced from commissioned turbines was sold since then at a fixed price average of $69.50 per megawatt-hour. (One megawatt can serve about 750 to 1,000 homes in New England; a megawatt-hour can serve 1,000 homes for one hour.)


Another celebratory headline, but what exactly is new? Vineyard Wind’s 62 turbines were installed by March. The project was producing electricity long before this announcement, and its 20-year utility contracts took effect in April. October 29 marks final commissioning, not the first power delivered to New England.
This is a roughly $4.5 billion industrial installation 15 miles off our coast. Its advertised 800-megawatt capacity is maximum output, not electricity produced around the clock. Massachusetts projects $1.4 billion in customer savings over 20 years, but those are forecasts, not verified household savings.
We’ve already had a 2024 blade failure that scattered fiberglass and foam onto Nantucket beaches, leading to a $10.5 million settlement between Nantucket and GE Vernova. Federal investigators have warned of gaps in offshore-wind oversight and uncertainty over cumulative environmental impacts.
Where are the public figures showing actual electricity delivered, turbine downtime, ratepayer savings, impacts on marine life, and long-term maintenance and removal costs? Commercial fishermen deserve transparent information about disruptions to their livelihoods, too.
I’m not dismissing the electricity being generated. I’m questioning whether “fully operational” is being mistaken for “problem solved.”
The real story begins after the celebration.
The average output of cheap corvette is 500 horsepower, the average running output is 48 horsepower.
How do you verify the future? Wait and see?
One ‘infant mortality’ blade failure out 186. What is the failure rate of jet engine turbine blade failures? Deaths resulting?
50%(?) of the $10.5 million went to the Nantucket lawyers. How much did the clean up cost the County of Nantucket? GE Verona settled not based on merit but on net cost to GE Verona.
Of the $ 10.5 million ‘received’ by Nantucket how much did Nantucket spend o the blade cleanup?
What is the impact on fishing? Is the catch down?
Albert, your Corvette analogy actually reinforces my point. A car’s rated horsepower isn’t its everyday output, just as a wind farm’s 800-megawatt capacity isn’t its measured generation. That’s exactly why I asked for actual production figures.
As for your one-in-186 blade calculation, that’s an incident count, not an established long-term failure rate. Federal investigators confirmed a manufacturing defect, and GE Vernova itself announced plans to remove some blades and reinforce others. Hardly grounds for waving the problem away as simple “infant mortality.”
And your suggestion that half Nantucket’s $10.5 million settlement went to lawyers? The Nantucket Current reported roughly $8.5 million reserved for community claims after legal and administrative expenses. Cleanup costs are a separate question; I haven’t claimed to know their total.
Regarding fishing, I never asserted that catches had fallen. I asked for evidence about impacts. Monitoring is how we find out.
Future savings can’t be verified in advance. Forecasts can, however, be tested against actual electricity production, bills, and costs as data accumulate.
Albert, your horsepower analogy supports my request for measurements, and your settlement estimate lacks support. Perhaps we could start with the facts rather than guessing at them.
Do you ask for the actual output figures of the 500 advertised HP output of a corvette engine?
An airliner jet engine?
What is the world wide wind turbine blade failure rate? Google tells me it is .5%. Do you have a better source?
The Vineyard Wind blades were manufactured in a new facility, based on analysis of the failed blade they have changed their manufacturing process.
The infant mortality was caused by the inadequate process.
Engineers understand that.
Only $1.5 million went to the lawyers?
How much went to the actual cleanup?
Where is the rest?
Did Nantucket win the liability lottery.
What other impact to fishing is there beyond the catch?
Should we wait until the data is collected before making a decision to shut down Vineyard Wind?
What are your facts? Guesses?
Supplementing fossil with wind is a matter of vision. Can you see Vineyard Wind from your place
And Albert, you ask whether I can see Vineyard Wind from my place. No, I can’t. But let me tell you what I can no longer see. For years, coming over the bridge into Vineyard Haven offered one of the most magnificent sights on this Island. The harbor opened up before you, filled with beautiful vessels, their masts, hulls, and rigging creating a scene that never grew old. Today, much of that view is blocked by the massive marine infrastructure built to support Vineyard Wind. Steel structures, bulkheads, and industrial facilities now dominate what was once a glorious panorama. In places, all you can see are the tops of the masts. You speak of vision, Albert. Well, some of us remember the vision we had before all that steel went up. And no amount of electricity generated will ever give us that view back.
Albert, manufacturers advertise maximum horsepower; engineers measure actual performance. That’s precisely why an 800-megawatt rating shouldn’t be confused with electricity delivered.
Your worldwide 0.5% blade-failure figure needs a source, a time period, and a definition of “failure.” Minor blade repairs and catastrophic breakages aren’t interchangeable. At Vineyard Wind, GE Vernova’s response went beyond fixing one blade: the company removed other blades manufactured at the same factory.
On the settlement, roughly $8.5 million was set aside for community claims, including eligible cleanup expenses and business losses. I don’t know Nantucket’s final cleanup bill, and neither of us should pretend otherwise.
You asked what fishing impacts exist beyond catch totals. NOAA identifies displaced fishing grounds, added operating costs, damaged gear, radar interference, and navigation risks. Those are potential impacts to measure, not proof every one occurred here.
I never proposed shutting down Vineyard Wind. I asked for actual output and independently assessed consequences. As for whether I can see it from my house, visibility has nothing to do with accountability.
Albert, you keep asking where the evidence is while brushing past the agencies that have supplied it. Perhaps read their findings before dismissing the questions.